Engineering and planning, procurement, production and delivery of the complete plant engineering as well as installation and commissioning.
The contained metal elements are removed from the slag. The metal-free slag is used as building material for a new island.
Customer:
Remex Mineralstoff GmbH
Retention:
August 2014
Commissioning:
June 2015
Throughput:
600,000 Mg/a
Machines for metal separation:
- screens
- ADR modules
- magnets
- non-ferrous separator