Reference Plant Engineering

Mechanical-biological Treatment Plant

Poznan

Engineering and implementation planning, procurement, manufacture and delivery of machine and conveyor technology as well as assembly and commissioning of parts of a plant for mechanical and biological treatment.

Key Facts

Engineering and implementation planning, procurement, manufacture and delivery of machine and conveyor technology as well as assembly and commissioning of parts of a plant for mechanical and biological treatment.

Mechanical-biological Treatment

Poznan

  • Client:
    ZZO Poznan
  • Commissioning:
    October 2014
  • Handover of the system in operation:
    June 2016
  • Input:
    Biowaste / green waste -> digestate / green waste
  • Throughput:
    52.000 Mg/a
  • Mechanical processing with the help of:
    • Screening drum
    • Feed hopper with decompactor
    • Magnetic separator
    • Shredder
  • Biological treatment with the aid of:
    Dry fermentation in 7 tunnels (29 x 4.45 x 5.6), followed by tunnel composting in 7 tunnels (25 x 5.45 x 5)
  • Materials obtained for further processing:
    • Compost
    • Metal
  • Special components:
    Tunnel entry device (TEG)
  • Participating companies of the Eggersmann Group besides EAB:
    Eggersmann Polska

Gunnar Beyer
Sales Manager

Eggersmann Plant Engineering
Recycling plants

Phone +49 5734 6690-227
g.beyer(at)f-e.de