MBT Posen

Engineering and planning, procurement, production and delivery of machinery and materials handling as well as installation and commissioning of parts of a plant for mechanical and biological treatment.

Customer:
ZZO Poznan

Retention:
October 2014

Acceptance:
June 2016

Input:
Biowaste / Green waste -> Digestate / Loppings

Throughput:
12.000 Mg/a 12.000 Mg/a 22.000 Mg/a 6.000 Mg/a

Mechanical treatment:

  • Screendrum
  • Feed hopper with decompator
  • Magnetic separators
  • Shredder
Biological treatment:
Dry fermentation in 7 tunnels (29 x 4,45 x 5,6), then tunnel composting in 7 tunnels (25 x 5,45 x 5)

Materials for further processing:
  • Compost
  • Metal
Special components:
Tunnel filling unit

Participating companies of the Eggersmann Group besides EAB:
Eggersmann Anlagenbau Kompoferm Polska

Videos

MBT Posen

13.05.2016

Pictures

Areal View
Dosing bunker
Screen drum
Tunnel filling unit
Tunnel filling hall and fermenter
Tunnel filling hall and fermenter
Tunnel filling hall, fermenter, rotting tunnels and tunnel filling unit
Pipes on the roof of the plant